A project manager believe that modifying the cope of the project may provide added value ervice for the cutomer The project manager hould(  )

2023-10-10 04:03分类: 计算机类 阅读:

 

A project manager believes that modifying the scope of the project may provide added value service for the customer .The project manager should(  )

A.assign change tasks to project members B.call a meeting of the configuration control board C.change the scope baseline D.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline 收起答案
答案: D
本题解析:

项目经理认为调整项目范围可以给客户提供增值的服务,项目经理该怎么做。选项D是按照原先的基线,在确定完成一项改进项目会得到客户的相应资金前,暂缓修改。