A project manager believe that modifying the cope of the project may provideadded value ervice for the cutomer.The project manager hould()

2023-10-10 04:04分类: 计算机类 阅读:

 

A project manager believes that modifying the scope of the project may provideadded value service for the customer.The project manager should()

A.assign change tasks to project members B.call a meeting of the configuration control board C.change the scope baseline D.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline 收起答案
答案: D
本题解析:

项目经理认为调整项目范围可以给客户提供增值服务,项目经理应该怎么做。选项 A 是安排任务变更到项目成员,选项 B 是召集变更控制委员会会议,选项 C是变更项目基线,选项 D 是按照原先基线,在确定完成一项改进项目会得到客户相应资金前,暂缓修改。由于是在原内容基础上增加增值服务内容,超出原先范围,应先确定客户认可和增加新资金,因此应选择 D。

郑重声明:喝茶属于保健食品,不能直接替代药品使用,如果患有疾病者请遵医嘱谨慎食用,部分文章来源于网络,仅作为参考,如果网站中图片和文字侵犯了您的版权,请联系我们处理!

上一篇:A project manager believe that modifying the cope of the project may provide added value ervice for

下一篇:A企业最近将现有客户关系系统迁移至虚拟化平台,并对应用软件进行全面 功能性升级。针对该过程,( )不能保证满足可用性、连续性。

相关推荐

推荐阅读

关注我们

    学哈答题
返回顶部